THE REGIONAL MUNICIPALITY OF PEEL
 
BY-LAW NUMBER 22-2012
 

A by-law to authorize the construction of a sanitary sewer on Portway Avenue, including Atrium Court, in the City of Mississauga, Ward 8, and undertake such work as a local improvement.


WHEREAS, the owners of properties abutting on Portway Avenue in the City of Mississauga, as set out in Schedule A to this by-law, have petitioned for the construction of a sanitary sewer on Portway Avenue from 2150 Portway Avenue to 2219 Portway Avenue, including Atrium Court, in the City of Mississauga, Ward 8, hereinafter referred to as "the Works";

AND WHEREAS, the Regional Clerk has certified that the petition for undertaking the Works is sufficient pursuant to the requirements set out in Ontario Regulation 586/06 Local Improvement Charges - Priority Lien Status, under the Municipal Act, 2001, hereinafter referred to as "the Regulation";

AND WHEREAS, notice of the Region of Peel’s intention to pass a by-law to undertake the Works as a local improvement at the meeting of Regional Council on March 29, 2012, was given to the public and to the owners of the affected lots in accordance with the requirements of the Regulation;

AND WHEREAS, the Council of the Regional Corporation has by Resolution 2012-288 passed on February 9, 2012 authorized the construction of the Works under Capital Project 12-2701;

NOW THEREFORE, the Council of the Regional Corporation enacts as follows:

  1. That the Regional Corporation shall construct the Works at a total estimated cost of $420,000 (excluding taxes);

  2. That the Regional Corporation shall undertake the Works as a local improvement for the purpose of raising part of the cost of the Works by imposing special charges on lots abutting on the Works and/or immediately benefiting from the works in accordance with the provisions set out in the Regulation;

  3. That the Commissioner of Public Works or the consulting engineer for the Regional Corporation shall take such action as may be necessary for the preparation of a contract or contracts for the execution of the Works under their supervision;

  4. That pursuant to the Regulation, the total cost of the Works shall be financed as follows:

a) $321,216.00 shall be the owners’ share of the cost, and shall be specially charged upon the land abutting directly on the Works and/or immediately benefiting from the works as set out in Schedule A attached hereto; and

b) $98,784.00 shall be the Regional Corporation’s share of the cost, which shall be funded from the Wastewater Capital Financing Stabilization Reserve (R0242), under Capital Project 12-2701.


READ THREE TIMES AND PASSED IN OPEN COUNCIL this 29th day of March, 2012.

C.Reid
________________________

Regional Clerk

E. Kolb
______________________

Regional Chair

 