For Immediate Release
January 26, 2001

Willy Lising
Project Manager
Public Works
Region of Peel
905-791-7800, Ext. 4574


(Bolton) - The Region of Peel will be installing a 750mm feedermain through the months of January to July on Mayfield Road and Coleraine Drive for the purpose of improving water supply to Bolton.

The watermain is going to be constructed in four separate contracts, as follows:

Mayfield Rd., from Heartlake Rd. to Torbram Rd. - Feb. 5 - June 30, 2001
Mayfield Rd., from Torbram Rd. to Goreway Dr. - Jan. 29 - June 16, 2001
Mayfield Rd., from Goreway Rd. to Coleraine Dr. - Feb. 12 - July 7, 2001
Coleraine Dr., from Coleraine Dr. to Holland Dr. - Feb. 19 - July 31, 2001

Traffic will be reduced to one lane in the immediate area of construction, and as a result traffic delays can be expected.

Access to properties near the construction may be interrupted from 8 a.m. to 7 p.m.; however, 24 hours notice will be given to residents.

For more information, please contact W. Lising, Project Manager at the Region of Peel, 905-791-7900, Ext. 4574.


- 30 -

Communication Services, 10 Peel Centre Dr., Brampton, ON L6T 4B9
Phone: 905-791-7800, Fax: 905-791-0595 , e-mail

| Home | News ReleasesCorporate Overview | Regional Departments |
Regional Council | Maps | Search |