Notice of Completion
Streetsville Watermain Replacements

Area Map

The Study
The Region of Peel has completed a Municipal Class Environmental Assessment (Class EA) study for watermain replacement to improve water quality and reliability of the water distribution system between Old Pine Street, Reid Drive, Queen Street and the section that currently crosses the Credit River.

The Class EA determined the preferred alternative for the watermain replacements is to construct new 400-mm watermains along Church Street, through the park and Credit River valley lands from Church Street to Reid Drive and along Reid Drive to Queen Street South. The preferred alternative also includes downsizing of the existing watermain along Queen Street South to 300-mm.

Project File Report
A Project File Report (PFR) documenting the study for this Class EA is available for review for thirty days (30) calendar days beginning May 22, 2013 at the following locations. It is also available on the Region of Peel website at: peelregion.ca/pw/water/environ-assess/streetsville.htm.

Region of Peel
Clerk’s Department
10 Peel Centre Drive
Suite A, 5th Floor
Brampton
Mon. to Fri, - 8:30 a.m. to 4:30 p.m.
Streetsville Library
112 Queen Street South
Mississauga
Tues./Thurs. - 10 a.m. to 9 p.m.
Fri. - 10 a.m. to 6 p.m.
Sat. - 9 a.m. to 5 p.m. Sun. - 1 p.m. to 5 p.m.

Comments:
Should you have any concerns with this project please provide written comments to Darrin Dodds at the address below within the review period of May 22, 2013 and June 21, 2013.

If concerns arise during the prescribed review period that cannot be resolved in discussion with the Region of Peel a request that the Minister of Environment make an order for the project to comply with Part II of the Environmental Assessment Act can be made. This would then be subject the project to an individual environmental assessment. This request (commonly referred to as a Part II Order or “bump up” request) must be received within the 30-day calendar review period by the Minister at the address listed below:

The Honourable Jim Bradley
Minister of the Environment
77 Wellesley Street West
11th Floor, Ferguson Block
Toronto, ON M7A 2T5

A copy of the request must also be sent to Darrin Dodds at the Region of Peel. If no requests are sent to the Minister of the Environment and received by June 21, 2013, the Region will proceed with the detailed design and construction of the watermain replacements as outlined in the project file.

Darrin Dodds, P.Eng.
Program Manager

10 Peel Centre Drive, Suite B, 4th Floor
Brampton, ON L6T 4B9
Tel: 905-791 7800 ext. 7823
Fax: 905-791-1442
Email: darrin.dodds@peelregion.ca

Information will be collected in accordance with the Freedom of Information and Protection of Privacy Act. With the exception of personal information, all comments will become part of the public record.

The Region of Peel is committed to ensure that all Regional services, programs and facilities are inclusive and accessible for persons with disabilities. Please contact the Project Manager if you need any disability accommodations to participate in the PIC.

This notice was first issued on May 22, 2013.



 

evised: Tuesday May 21 2013