Brampton | Caledon | Mississauga
The following list provides details on Capital projects currently progressing in Brampton.
Information Last Updated: March 19, 2012
| Street | Description | Scheduled Commencement |
|---|---|---|
| Hwy 50 From Ebenezer Road to Old Castlemore Road |
Reconstruction | May 2012 |
| Countryside Drive east of Torbram Road | Sanitary Sewer and Watermain Installation | March 19, 2012 |
| Rutherford Road South and First Gulf Boulevard | Installing new 2100mm Feedermain | February 2012 |
| Bovaird Drive at Torbram Road | Intersection Improvements | November 2011 |
| Creditview Road, Sandalwood Parkway to Crown Victoria Drive | Watermain Installation | October 2011 |
| Humberwest Parkway and Goreway Drive | Watermain Construction Project, Contract 1 | September 2011 |
| Epsom Downs Drive, Eringate Road, Fidelia Crescent | Watermain Replacement and Improvement | September 2011 |
| Northwood Drive, Torbram Road, Rutherford Road and Finley Road on Orenda Road | Watermain Replacement and Improvement | September 2011 |
| Various locations | Watermain Replacement and Improvement | August 2011 |
| Ebenezer Road adjacent to Hwy 50 | Sanitary Sewer | June 2011 |
| Highway 50 | Reconstruction from Highway 7/Queen Street East to Ebenezer Road | June 2011 |
| Wanless Road and Creditview Road | Watermain and Sanitary Sewer | October 2010 |
| Winston Churchill Boulevard | Reconstruction from Steeles Avenue to Embleton Road and Installation of a 400mm Watermain | October 2010 |
| Various Locations | Watermain Replacement – ISF Assignment Contract 4 |
October 2010 |
| Joseph and Thomas Streets | Construction of Sanitary Sewers | September 2010 |
| Gore Road from Cottrelle Boulevard to Castlemore Road | Road Improvements | September 2010 |
| Bramalea Road from Derry Road to Highway 407 | Watermain Replacement | August 2010 |
| First Gulf Boulevard from west of Biscayne Crescent to Kennedy Road South | Installing new feedermain | August 2010 |
| Goreway Drive between Mayfield Road and Countryside Drive | Installation of a new watermain | July 2010 |
| Kennedy Road and Courtleigh Square | Installation of a new watermain | April 2011 |
| Mcvean Sanitary Trunk Sewer Construction | Construction of the sanitary trunk sewer on McVean Drive between Castlemore Road and Countryside Drive | May 2010 |
| Intermodal Drive, Brampton. | Intermodal Sewage Pumping Station Upgrades | April 2010 |
| Future Williams Parkway at Mississauga Road | Watermain Construction | February 2010 |
| Creditview Road, Hallstone Road, Churchville Road and Martin's Boulevard | Credit Valley Trunk Sewer Construction | October, 2006 (updated May 07) |
| Future Williams Parkway | Trunk Watermain & Local Watermain | February, 2010 |