Public Works Construction

Construction in Peel: Brampton

Watermain Installation
Mayfield Road from North Brampton Pumping Station to East of Heart Lake Road
Capital Projects 10-1966, 13-1903 and 07-1506


We have finished the work. The project is under warranty until November 2017.

What are we doing?

  • Modifications to the North Brampton Pumping Station and installation of a 900-mm feedermain from the pumping station to approximately 100m east of Heart Lake Road, as shown on the attached map.
  • Some of the watermain will be installed by open cut, and a small portion will be tunnelled from inside the pumping station property to a shaft on Mayfield Road.

Why?

  • To provide improved hydraulics and water storage to residents of Brampton and Caledon.

When?

  • The work will be starting mid-September 2014.
  • The project should be completed by April 2015.
  • We will start restoring the road when all water system installation is complete, and as weather permits.

Who can you call?

Region of Peel Personnel
Contact Responsibilities Phone Number
Troy Leyburne Project Manager 905-791-7800, ext. 7919
Carman Plester Region Inspector 905-791-7800, ext. 3246
CIMA/GM BluePlan - Consultant
Contact Responsibilities Phone Number
Sean Steele Contract Administrator 289-288-0287
Rino Campana Site Inspector 519-239-3860
Kingdom Construction Limited
Kingdom Construction will do the work, under contract to the Region of Peel
Contact Responsibilities Phone Number
Wade Lee Project Manager 519-240-2710
Clarence O’Connor Project Superintendent 519-277-8695

Working Hours

  • Our contractor’s normal working hours are from 7 a.m. to 7:00 p.m. We apologize for any inconvenience this may cause, but a shorter working day would mean the project would take longer to complete.

Traffic, Parking Control and Driveway Access

  • We may need to reduce traffic to two lanes in each direction during construction.
  • The Traffic Control Plan will affect driveway access from Mayfield Road to allow right turns only.
  • We will make sure businesses have access at all times.

Project Updates

  • The Region of Peel will always let you know if there are any major changes to the plans.
  • We will try to disturb you as little as possible.
  • Please call the Project Manager if you have any problems or special needs.

Interrupting Your Water Supply

  • We do not anticipate needing to interrupt your water supply; however, if it is necessary, we will provide 48 hours’ (2 days) notice before we need to shut off your water.

Vibrations

  • You may feel slight vibrations from the construction work in your home or business.

Email questions or comments

| Back to Brampton Construction Projects |

Revised: Monday July 11 2016

www.peelregion.ca

Home | Contact Us | Search | A-Z Topic List
Privacy & Terms of Use | Service Commitment

Smaller Text Larger Text