Public Works Construction

Construction in Peel: Caledon

Widening and Reconstruction of Mayfield Road
from Bramalea Road to Airport Road
Project #06-4040

What are we doing?

  • Widening and reconstruction of Mayfield Road between Bramalea Road and Airport Road; including new curb and multi-use trail. View attached map.
  • Removing and replacing existing culverts.
  • Construction of a new bridge east of Torbram Road (for existing creek); including the relocation of 150m of existing watermain.
  • Installation of storm sewers and outlets.
  • Installation of local watermains for future side streets.
  • Installation of new street lighting.
  • New traffic signals at Mayfield Road and Torbram Road.

Where?

  • Mayfield Road between Bramalea Road (250m east) and Airport Road, approximately 2.5km.

When?

  • Start: July 10, 2017
  • Finish: September 2019

Who can you call?

  • The work will be performed by Four Seasons Site Development with Contract Administration services provided by IBI Group on behalf of the Region of Peel. The contact names and telephone numbers are listed below:
Region of Peel Personnel
Contact Responsibilities Telephone
Dan Bennington Project Manager 905-791-7800, ext. 7811
Ommar Moeen Construction Inspector 647-643-3627
Four Seasons Site Development
under contract to the Region of Peel
Contact Responsibilities Telephone
Marco Marrone Project Manager 416-525-5099
Kyle Rollinson Site Superintendent 416-678-4043
IBI Group
under contract to the Region of Peel
Contact Responsibilities Telephone
Elizabeth Kadela Project Manager 416-526-6996
Andrew Lennox Contract Administrator 647-463-3743

Working Hours

  • Our contractor’s normal working hours are from 7AM to 7PM.
  • These hours are consistent with the local municipality’s by-laws. We understand this may cause some inconvenience, but a shorter working day would mean the project would take longer to complete.

Traffic and Parking Control

  • Temporary lane closures will be required during non-peak hours.
  • Emergency access will be maintained at all times.
  • Barriers and signs will be placed for safety and direction, as required under the Occupational Health and Safety Act.

Driveway Access

  • We anticipate that driveway access will be maintained in so far as possible.
  • If we need to block your driveway for a short time you will be contacted to arrange for the best time and for alternate access.
  • We will ensure businesses have access at all times.
  • Please call the Project Manager if you have special needs related to access or business hours.
  • Address tabs and mail boxes will be relocated.

Project Updates

  • The Region of Peel will keep you informed of any substantial changes in the project scope or schedule.
  • We are committed to ensuring minimum disruption to your homes and businesses.
  • Please call the project manager if you have any special needs.

Email questions or comments

| Back to Brampton Construction Projects |

Revised: Friday September 08 2017

www.peelregion.ca