Construction in Peel: Caledon

Palgrave Road Improvements
Highway 50
Project 17-4645

What are we doing?

  • Construction of sidewalks and a pedestrian crossover to improve public safety, accessibility, and connectivity, in addition to minor road reconstructions. The work includes, but is not limited to:
    • clearing and grubbing;
    • excavation and grading;
    • storm sewer replacements;
    • placement of curbs and sidewalks;
    • electrical works;
    • paving;
    • restoration; and
    • minor related works.

Public Consultation

Where?

  • Highway 50, Patterson Side Road/Gibson Lake Drive to Buckstown Trail
  • Patterson Side Road, Highway 50 to Darrowby Crescent
  • Church Street East, Highway 50 to Wallace Avenue
  • Maple Lane, Birch Avenue to Pine Avenue
  • View attached map

When?

  • Start: week of October 02, 2017
  • Finish: end of November 2017, weather permitting

Who can you call?

Rafat General Contracting Inc.
under contract to the Region of Peel
Contact Person Responsibilities Telephone Number
Laith Azzo Project Manager 416-771-6184
Jassim Arabo Site Supervisor 416-301-6218
Region of Peel
Contact Person Responsibilities Telephone Number
Manvir Tatla Project Manager 905-791-7800, ext. 7998
Marc Vaccari Construction Inspector 905-791-7800, ext. 3246/47

Working Hours

  • Our Contractor’s working hours are from 7:00am to 5:00pm, Monday to Friday. The Contractor is also permitted to work on Saturdays if they choose to.
  • These hours are consistent with the local municipality’s bylaws. We understand this may cause some inconvenience, but a shorter working day would mean the project would take longer to complete.

Traffic Control

  • Temporary lane closures will be required during non-peak hours.
  • All intersections will remain open but temporary lane closures will be necessary.
  • Ontario Provincial Police will be present during lane closures at all intersections to direct traffic safely.
  • Emergency access will be maintained at all times.
  • Barriers and signs will be placed for safety and direction, as required under the Occupational Health and Safety Act.

Driveway Access

  • We will ensure residents and businesses have access at all times.

Project Updates

  • The Region of Peel will keep you informed of any substantial changes in the project scope or schedule.
  • We are committed to ensuring minimum disruption to your homes.
  • Please call the Project Manager or Inspector if you have any questions or concerns.