Public Works Construction

Construction in Peel: Caledon

Palgrave Road Improvements
Highway 50. Patterson Side Road to Buckstown Trail
Project 17-4645

What are we doing?

  • Construction of sidewalks and a pedestrian crossover to improve public safety, accessibility, and connectivity, in addition to minor road reconstructions. The work includes, but is not limited to:
    • clearing and grubbing;
    • excavation and grading;
    • storm sewer replacements;
    • placement of curbs and sidewalks;
    • electrical works;
    • paving;
    • restoration; and
    • minor related works.

Where?

  • Highway 50, Patterson Side Road/Gibson Lake Drive to Buckstown Trail
  • Patterson Side Road, Highway 50 to Darrowby Crescent
  • Church Street East, Highway 50 to Wallace Avenue
  • Maple Lane, Birch Avenue to Pine Avenue
  • View attached map (PDF)

When?

  • Start: October 02, 2017
  • Finish: June 15, 2018, weather permitting

Who can you call?

Rafat General Contracting Inc.
under contract to the Region of Peel
Contact Person Responsibilities Telephone Number
Laith Azzo Project Manager 416-771-6184
Jassim Arabo Site Supervisor 416-301-6218
Region of Peel
Contact Person Responsibilities Telephone Number
Serguei Kabanov Project Manager 905-791-7800, ext. 8754
Marc Vaccari Construction Inspector 905-791-7800, ext. 3246/47

Working Hours

  • Contractor’s normal working hours are from 7:00am to 5:00pm, Monday to Friday. Some work may occur on Saturdays, from 7:00am to 5:00pm.
  • These hours are consistent with the local municipality’s bylaws. We understand this may cause some inconvenience, but a shorter working day would mean the project would take longer to complete.

Traffic Control

  • Temporary lane closures will be required during non-peak hours.
  • All intersections will remain open but temporary lane closures will be necessary.
  • Ontario Provincial Police may be present during lane closures to direct traffic.
  • Emergency access will be maintained at all times.
  • Barriers and signs will be placed for safety and direction, as required under the Occupational Health and Safety Act.

Driveway Access

  • We anticipate that driveway accesses will be maintained.
  • Completing some of the works (such as curb replacement) may result in your driveway being temporary inaccessible. If this is the case, we will contact you in advance to arrange timing and alternate access. If your driveway is inaccessible, you may choose to park on a side street temporarily.
  • Please call the Project Manager if you have any special needs related to access.

Project Updates

  • The Region of Peel will keep you informed of any substantial changes in the project scope or schedule.
  • We are committed to ensuring minimum disruption to your homes and businesses.
  • Please call the Project Manager or Inspector if you have any questions or concerns.