Natural creek channel realignment and restoration to sensitive areas

Seeding and tree and shrub planting

We have finished the work. The project is under warranty until May 2018.

The Region of Peel will be working in your neighborhood along Turtle Creek on the existing sanitary sewer including maintenance holes (see attached map and schedule below). The work includes natural creek channel realignment and restoration in sensitive areas; seeding and tree and shrub planting.View area map (PDF).

This work is to protect existing wastewater services. Wastewater comes from flushing toilets, having a shower or washing dishes. Sanitary sewer pipes take wastewater from homes or businesses to a treatment plant.

Reducing the impact of construction

Safety

The Region of Peel provides a safe environment that conforms to theOccupational Health and Safety Act,at all times.

Schedule

Construction of this project is expected to start on January 7, 2016 and be substantially completed by the end of January 2016. Final restoration work will begin in April 2016 and will be completed within two weeks.

Contact

The Region encourages you to notify us if you have special requirements, or if you have any comments or issues. Please contact:

Joanna Pietkiewicz
Project Manager
Wastewater Division
905-791-7800, ext. 7815