Public Works Construction

Construction in Peel: Mississauga

Hot Mix Asphalt Resurfacing on Derry Road from Dixie Road to Torbram Road and from Hull Street to Professional Court
Project #15-4665

We have finished the work. The project is under warranty until December 2017.

Project Description

The Region of Peel will be carrying out the resurfacing of Derry Road East from Dixie Road to Torbram Road and from Hull Street to Professional Court to improve asphalt performance. The work to be done includes, but is not limited to, cold milling, grading, hot mix paving, removal and replacement of curbs, repairs and adjustments to structures, placement of permanent thermoplastic pavement markings, restoration, and minor related works. (see map).

Schedule

The work is scheduled to commence on or about May1, 2015 and we anticipate completion of the works by the end of August, weather permitting.

Contact Persons

The works will be performed by Graham Bros. Construction Limited. The contact names and telephone numbers are listed below.

Contractor Personnel (Graham Bros. Construction Limited)
Contact Responsibilities Phone Number
Kevin Hutchinson Project Manager 416-346-6843
Rodney Palmateer Superintendent 416-522-7071
Region of Peel Personnel
Contact Responsibilities Phone Number
Serguei Kabanov Project Manager 905-791-7800 ext. 8754
Marc Vaccari Construction Inspector 905-791-7800 ext. 3246/47

Traffic And Parking Control

The works will be staged to minimize disruption to traffic and businesses. Most work will be undertaken at night time. Temporary lane closures will be required during non-peak hours. Peel Regional Police will be present to direct traffic safely. Emergency access will be maintained at all times. Barriers and signage will be erected to direct traffic safely through the construction zone, as required under the Occupational Health and Safety Act.

Project Updates

The Region of Peel is committed to keeping you informed and ensuring that the works are carried out with minimum disruption. If there are any substantial changes in the project scope or schedule, you will be provided with project updates. We also encourage you to notify the appropriate contact person to advise them of any problems or particular needs. We thank you in advance for you cooperation and patience during the construction of this project.

Sk

c.t.: Councillor C. Parrish

Email questions or comments

| Back to Mississauga Construction Projects |

Revised: Wednesday May 04 2016

www.peelregion.ca

Home | Contact Us | Search | A-Z Topic List
Privacy & Terms of Use | Service Commitment

Smaller Text Larger Text