What are we doing?

  • Replacing and improving the aging sanitary sewer along Freeport Drive and Anniversary Road as shown on the attached map.
  • Replacing the sanitary sewer pipe and services to property line.

Why?

  • To upgrade the sanitary sewer capacity and reliability as part of the Region of Peel’s State of Good Repair program.

When?

  • We expect to start work on or about October 24, 2016, starting at Freeport Drive.
  • The project should be completed before July 1, 2017. We will start restoring the road when all sanitary sewer replacements and transfers are complete, and as weather permits.

Who can you call?

Region of Peel Personnel
Contact Responsibilities Phone Number
Derek Gorzynski Project Manager 905-791-7800, ext. 5013
Rene Gomez Inspector 905-791-7800, ext. 3246
Mastercrete Construction Inc.
Mastercrete Construction Inc. will do the work, under contract to the Region of Peel
Contact Responsibilities Phone Number
Matthew Fusillo Project Manager 905-890-8889
Frank Fusillo Site Superintendent 905-890-8889

Working Hours

  • Our contractor’s normal working hours are from 7 a.m. to 7 p.m. These hours are consistent with the local municipality’s bylaws. We understand this may cause some inconvenience, but a shorter working day would mean the project would take longer to complete.

Traffic and Parking Control

  • We may need to reduce traffic to a single lane during construction.
  • We may need to close the streets temporarily to ensure safety of the public and to accelerate the construction. If we have to reroute traffic, we will place signs giving directions
  • On-street parking will be allowed under the City of Mississauga Parking Enforcement Permit # 37806.
  • On-street parking will be reduced in the immediate vicinity of the construction zone.

Driveway Access

  • Due to construction activities, we may need to block your driveway for a short time. We will contact you before we do this to arrange for the best time and for alternate access, if needed. If your driveway is blocked, you may choose to park on a side street for a short time. If you need immediate access to your driveway, the contractor will have road plates available to quickly allow access in and out of your driveway.

Irrigation or Sprinkler Systems

  • Please tell the inspector if you have underground irrigation or a sprinkler system outside your property line.
  • You may wish to move the sprinkler lines to inside your private property to avoid damage.

Trimming Trees

  • If tree branches within the right-of-way interfere with construction, the contractor will have the trees pruned before equipment enters the drip line of the tree.
  • If tree branches on private property interfere with construction, they will be pruned back to the nearest suitable trunk, crotch or branch.
  • The contractor will ask you for permission before cutting any branches on private property. If you do not allow the contractor onto your property to trim the branches, the branches will be cut vertically at the property line.

Waste Collection

  • Your garbage, recycling and organics containers will continue to be picked up on your regularly scheduled day. It is the contractor’s responsibility to move your garbage, recycling and organics bins to a location where our collection vehicles can pick them up. Empty containers will be returned to their corresponding addresses. Please make sure your house number is clearly marked on each bin.

Vibrations

  • You may feel slight vibrations from the construction work.

Replacing and Taking Care of Your Sod

  • The contractor will take care of any sod we replace for 30 days.
  • You can help the sod to stay healthy by watering it for one hour in the early morning, two or three times a week. This is especially important in hot or dry weather.
  • We will replace your sod as soon as we can, but there may be a short delay.
  • It is very common for the work area to settle a bit following construction. If you notice any settlement, please let the project manager or inspector know and we will ensure the contractor fixes it.

Repairing Your Driveway

  • If we need to cut your driveway to replace the existing service, we will repair the asphalt in the disturbed area from edge to edge across the driveway. Unfortunately the Region cannot completely replace your driveway.
  • If you have any concerns, please call the Project Manager.
  • We will repair your driveway as soon as we can, but there may be a short delay.

Repairing the Road, Curbs, and Sidewalks

  • We will start restoring the road and boulevard once all replacements and service transfers are complete and as weather permits.
  • We will complete the restoration on a street-by-street basis.

Project Updates

  • The Region of Peel will always let you know if there are any major changes to the plans.
  • We will try to disturb you as little as possible.
  • Please call the project manager or inspector if you have any concerns or special needs.

Email questions or comments

| Back to Mississauga Construction Projects |

Revised: Wednesday October 19 2016

www.peelregion.ca

Home | Contact Us | Search | A-Z Topic List
Privacy & Terms of Use | Service Commitment

Smaller Text Larger Text