Project update #7

Major Paving Operations - Dundas to QEW

Please be advised that Gazzola Paving re-scheduled Paving Operations on Winston Churchill Boulevard, between North Sheridan Way/Upper Middle Road E and Sheridan Park Drive/Plymouth Drive, in both directions for this weekend, September 10-11, 2016, weather permitting. The intent is to complete placement of top asphalt at both intersections over the weekend.

Paving operations will commence in the Northbound direction, starting North of QEW.

Below is the revised schedule:

Date Time Direction Street Activity
September
10 11
Day (07:00am to 7:00Ppm) Northbound direction, followed by Southbound direction South of North Sheridan Way to North of Sheridan Park Drive Top Asphalt
September
12 14
Day (07:00am to 7:00Ppm) Northbound direction, followed by Southbound direction North of Sheridan Park Drive to South of Dundas Street W Top Asphalt
September
16 17
Night (7:00pm to 07:00am) Southbound, Northbound, Eastbound and Westbound Royal Windsor Drive Intersection Full Depth Milling/
Top Asphalt
September 17 Day (07:00am to 7:00Ppm) Southbound, Northbound, Eastbound and Westbound Royal Windsor Drive Intersection Full Depth Milling/
Top Asphalt
September
17 18
Night (7:00pm to 07:00am) Southbound, Northbound, Eastbound and Westbound Royal Windsor Drive Intersection Full Depth Milling/
Top Asphalt
September 18 Day (07:00am to 7:00Ppm) Southbound, Northbound, Eastbound and Westbound Royal Windsor Drive Intersection Full Depth Milling/
Top Asphalt

The following sequence of events will occur on site:

Southbound direction:

Northbound direction: