Construction Progress

Work on the 2400-mm Hanlan Feedermain (HFM) and the 1500-mm Mississauga City Centre Subtransmission Main (MCC) is well underway!

HFM & MCC Tunnel Shaft Excavation

Location Completed In Progress
Lakeshore Rd / Lakefront Prom  
Lakeshore Rd / Dixie Rd  
Dixie Rd / South Service Rd  
Dixie Rd / Primate Rd  
Dixie Rd / Golden Orchard Dr  
Eastgate Pkwy / Etobicoke Creek  
Eastgate Pkwy / Tomken Rd  
Tomken Rd / 401  
Tomken Rd / Britannia Rd  


HFM Tunnel Excavation

Location Completed In Progress
Lakefront Prom: Lakeview WTP – Lakeshore Rd  
Lakeshore Rd: Lakefront Prom – Dixie Rd  
Dixie Rd: Lakeshore Rd – Golden Orchard Dr  
Eastgate Pkwy: Tomken Rd – W of Etobicoke Creek  
Tomken Rd: Eastgate Pkwy – South of 401  
Tomken Rd: South of 401 – Hanlan Pumping Station  


MCC Tunnel Excavation

Location Completed In Progress
Tomken Rd: Eastgate Pkwy – South of 401  
Tomken Rd: South of 401 – Hanlan Pumping Station  


HFM Pipe Installation

Location Completed In Progress Not Started
Lakefront Prom: Lakeview WTP – Lakeshore Rd    
Lakeshore Rd: Lakefront Prom – Dixie Rd    
Dixie Rd: Lakeshore Rd – Golden Orchard Dr    
Dixie Rd: Golden Orchard Dr – Eastgate Pkwy    
Eastgate Pkwy:  Tomken Rd – Dixie Rd    
Tomken Rd: Eastgate Pkwy – South of 401    
Tomken Rd: South of 401 – Hanlan Pumping Station    


MCC Pipe Installation

Location Completed In Progress Not Started
Hanlan Pumping Station – Tomken Rd: South of 401    
Tomken Rd: South of 401 – Eastgate Pkwy    
Eastgate Pkwy: Tomken Rd – Cawthra Rd    
Cawthra Rd: Eastgate Pkwy – 100m North of Burnhamthorpe Rd    
Cawthra Rd: 100m North of Burnhamthorpe Rd – Burnhamthorpe Rd    

Revised: Thursday March 16 2017