Twinning of the East Brampton trunk sewer

Hwy 407 and Steeles Ave East intersection to Goreway Drive and Humberwest Parkway. Project 11-2201

The Region is installing a new trunk sanitary sewer along Humberwest Parkway and Goreway Drive near Queen Street and generally southwards to Steeles Avenue west of Airport Road. This work is being done to upgrade the capacity and reliability of the sewer system in East Brampton.View area map (PDF).

Safety

The Region of Peel provides a safe environment that conforms to the Occupational Health and Safety Act, at all times.

Schedule

Work is underway and should be completed before April 2019. We will start restoring the road when all sewer system components are complete, and as weather permits. All work is under warranty for two years from the completion date.

Working hours

Our contractor’s normal working hours are from 7 a.m. to 7 p.m. Night work is anticipated to limit disruptions to traffic in the area. We understand this may cause some inconvenience, but shorter working days would mean the project would take longer to complete.

Traffic impacts

Goreway Drive north and south of Queen Street and Humberwest Parkway will be reduced to two lanes starting January 8, 2018. Reductions to a single lane are anticipated during working hours to complete certain project requirements between January and August 2018. Delays should be expected and traffic control signs and flag persons should be obeyed.

Pedestrian access/public transit

Pedestrian access to the north side of the intersection at Queen Street and Goreway Drive is anticipated to be closed from January 2018 to August 2018 and a detour via the south side of the intersection will be provided.

Brampton Transit stops may be temporarily relocated. Pedestrians should follow the posted signs to the nearest alternative or relocated stop location.

Contact

The Region of Peel encourages you to notify the project manager listed below if you have special requirements, comments or concerns. The Region of Peel will always let you know if there are any major changes to the plans.

Olena Gordiyenko
Project Manager
Wastewater Division
905-791-7800, ext. 7843

Email questions or comments