Stormwater management facility retrofits

Project 16-4033 Bovaird Drive and Gillingham Drive, City of Brampton, Project 17-4037S Mayfield Road and Kennedy Road, Town of Caledon. Project 17-4039S Mayfield Road and Heart Lake Road, City of Brampton

Project updates

  • We have finished the work. The project is under warranty until Febuary 2023.

Project description

The Region of Peel will be retrofitting three Stormwater Management Facilities. This work includes, but is not limited to:

Schedule

The work is scheduled to commence the week of August 28, 2017 and we anticipate completion of the works on July 31, 2020.

Contact

Nour Tabieh, Project Manager, 905-791-7800 ext. 7962

Traffic operations

The works will be taking place outside of the roadway. Existing traffic flows will be maintained during construction and emergency access will be maintained at all times.

Working hours

The Contractor’s working hours are from 7AM to 7PM, Monday to Friday. These hours are consistent with the local municipality’s bylaws.

Project updates

The Region of Peel is committed to keeping you informed and ensuring that the works are carried out with minimum disruption. If there are any substantial changes in the project scope or schedule, you will be provided with project updates. We thank you in advance for you cooperation and patience during the construction of these projects.