Public notice

Construction work starting in your neighbourhood Dundas St. West between Erin Mills Parkway and Mississauga Rd. Dundas Wastewater Diversion Project #08-2205.

Project updates

What we are doing

The Region of Peel will be constructing a large diameter trunk sanitary sewer by tunnelling underneath Dundas St. West between Erin Mills Parkway and Mississauga Road.

This trunk sanitary sewer work is to improve the existing wastewater service. Wastewater comes from flushing toilets, having a shower or washing dishes. Sanitary sewer pipes take wastewater from homes and businesses to a treatment plant.

When

Construction will start on, or about March 4, 2019. The entire project will take approximately 24 months to complete.

How this will impact you

Safety

The Region of Peel provides a safe environment that conforms to the Occupational Health and Safety Act, at all times.

Project facts

Contact

Please contact the project manager listed below if you have any comments or concerns.

Ajay Puri, M.E. (Env.), P.Eng.
Project Manager, Capital Works
Wastewater Division, Collection and Communal Treatment
905-791-7800, ext. 5073
Email Ajay Puri