Construction of 1050/1350MM sanitary sewer and 150MM watermain

Queensway/Hurontario area. Project 10-2425 and 14-1349

We have finished the work. The project is under warranty until January 2019.

What we are doing

Why

When

Who you can call

Region of Peel Personnel
Contact Responsibilities Phone Number
Grace Krasowski Project Manager Wastewater 905-791-7800, ext. 7820
AECOM
AECOM will administrate the work, under contract to the Region of Peel
David O’Gorman Contract Administrator 647-229-0934
Kevin Martin Inspector 416-884-5360
Drainstar Contracting Ltd.
Drainstar Contracting Ltd. will do the work, under contract to the Region of Peel
Mike Skrisantha Project Manager 416-990-0117
Tony Cota Site Superintendent 416-990-7780

Working hours

Traffic and parking control

Driveway access

Irrigation or sprinkler systems

Trimming trees

Interrupting your water supply

Vibrations

Replacing and taking care of your sod

Repairing your driveway

Project updates

Email questions or comments