Watermain replacement and improvements

South Sheridan Way and Indian Grove. Project 13-1347 H1

What we are doing

Restoring curb and sidewalk and paving the road on South Sheridan Way and on Indian Grove from South Sheridan way to approximately 20m south/east of Tim Hortons south/east entrance

When

Curb and sidewalk restoration will begin on Monday, November 8, 2021, starting on the south/west side of the road.

Paving will start in early December. As work depends on the weather, these dates may change.

What does this mean for you

Please make sure that the road is cleared of vehicles (and any type of materials) by 7 a.m.

You may not have access to your driveway for a short time during curb and sidewalk restoration. The Contractor will coordinate with affected residents. Residents may be asked to park on the opposite side of the street from the work.

Sign up for email notices to stay informed

If you would like to receive timely project updates right to your inbox please go to peelregion.ca/construction and click on “Sign up for Email Notices”. Updates will be provided as the work progresses.

We appreciate your co-operation during the completion of work and apologize in advance for any inconvenience. If you have any questions, please call me at 905-791-7800 x 7832.