Watermain replacement and improvements
South Sheridan Way and Indian Grove. Project 13-1347 H1
What are we doing?
- We have completed watermain replacements in your area with the exception of some watermain work on South Sheridan Way, a final connection piece at the south end of Indian Grove, and final restoration.
- Temporary restoration of curbs, sidewalks, and driveway aprons have been completed for the winter. Final restoration will be completed in spring 2022 including proper driveway restoration.
- We will shut down for the winter starting Friday, December 17, with some minor site clean up the week of December 20.
- We have left the construction site in a safe condition for the rest of the winter.
When will we be back?
- We expect to start work in mid-February to mid-March 2022, with final restoration in spring 2022.
- Works should be complete by July 2022.
Who can you call?
Region of Peel | ||
Contact Person | Responsibilities | Telephone Number |
---|---|---|
Nicole Sartor | Project Manager | 905-791-7800, ext. 7832 |
Avalon Myers | Project Ambassador | 416-457-3889 |
Brandon Vandermeer | Inspector | 647-824-9821 |
Rymall Personnel | ||
Bob Clarke | Project Manager (Contractor) | 416-745-0707 |
Project updates
- The Region of Peel will always let you know if there are any major changes to our plans.
- We will try to disturb you as little as possible.
- Please call the Project Manager, Project Ambassador, or Inspector if you have any problems or special needs.
Sign up for email notices to stay informed
- If you would like to receive timely project updates right to your inbox please go to peelregion.ca/construction and click on “Sign up for Email Notices”. Updates will be provided as the work progresses.
Construction project updates can be found at peelregion.ca/construction.
Follow Peel Public Works on Twitter for service updates and changes.