Construction work starting in your neighborhood

Project #17-2905S Hull St.

The Region of Peel will be working in your neighborhood to improve stormwater service by upgrading the Malton Four Corners Stormwater Pumping Station. The station is located at 2 Hull St. View area map (PDF). This work includes the construction of new underground wet well and valve chamber within Frank Mckechnie Park, and upgrades to the station equipment.

Schedule

Construction is expected to start at the site late October 2018 and will be substantially completed by the end of May 2020.

Reducing the impact of construction

Traffic, driveway and parking information

Trees

Park use

Safety

Contact

The Region encourages you to notify the Project Manager listed below if you have special requirements, or if you have any comments or concerns.