Watermain replacement and improvement
Paisley Boulevard West, Whaley Drive Easement, President Boulevard Easement and Consulate Road.
Project 19-1310 J
Project updates
What are we doing?
- Replacing and improving the aging watermain along Paisley Boulevard West, Whaley Drive Easement, President Boulevard and Easement, and Consulate Road. View area map (PDF).
- Replacing the water service pipe to your service box if it is connected to the replaced portion of watermain.
Why?
- To upgrade the water system capacity and reliability as part of the Region of Peel’s State of Good Repair program.
When?
- We expect to start work on or about February 17, 2020. We will start at Hurontario and Paisley Boulevard West.
- Watermain installation and restoration (asphalt, sod, etc.) should be completed before December 2020. All work is under warranty for two years from the completion date.
- We will start restoring the road when all water system replacements and transfers are complete, and as weather permits.
Who can you call?
Region of Peel | ||
---|---|---|
Contact Person |
Responsibilities |
Telephone Number |
Sarah Lobo |
Project Manager |
905-791-7800, ext. 8266 |
London Excavators and Trucking Ltd. |
||
Frank Carelli |
Site Super/Project Coordinator |
416-247-6601 |
Working Hours
- Our contractor’s normal working hours are from 7 a.m. to 7 p.m. These hours are consistent with the local municipality’s bylaws. We understand this may cause some inconvenience, but a shorter working day would mean the project would take longer to complete.
Traffic and Parking Control
- We may need to reduce traffic to a single lane during construction.
- If we have to re-route traffic, we will place signs giving directions.
- On-street parking will be reduced during construction.
Driveway Access
- Due to construction activities, we may need to block your driveway for a short time. We will contact you before we do this to arrange for the best time and for alternate access, if needed. If your driveway is blocked, you may choose to park on a side street for a short time. If you need immediate access to your driveway, the contractor will have road plates available to quickly allow access in and out of your driveway.
- We will make sure businesses have access at all times.
- Please call the Project Manager if you have special needs related to access or business hours.
Irrigation or Sprinkler Systems
- Please tell the inspector if you have underground irrigation or a sprinkler system outside your property line.
- You may wish to move the sprinkler lines to inside your private property to avoid damage.
Trimming Trees
- If tree branches within the right-of-way interfere with construction, the contractor will have the trees pruned before equipment enters the drip line of the tree.
- If tree branches on private property interfere with construction, they will be pruned back to the nearest suitable trunk, crotch or branch.
- The contractor will ask you for permission before cutting any branches on private property. If you do not allow the contractor onto your property to trim the branches, the branches will be cut vertically at the property line.
Interrupting Your Water Supply
- It is our goal to let you know 48 hours (2 days) in advance if we need to shut off your water. Occasionally, we may have to reduce this notice to 24 hours.
- For water interruption during service transfers, the contractor will notify you the day of the transfer as this will be a brief interruption. This will ensure proper notification for short duration works.
- If we have to shut off your water because of an emergency, we will do everything we can to fix the problem as quickly as possible.
Waste Collection
- Your garbage, recycling and organics containers will continue to be picked up on your regularly scheduled day. It is the contractor’s responsibility to move your garbage, recycling and organics bins to a location where our collection vehicles can pick them up. Empty containers will be returned to their corresponding addresses. Please make sure your house number is clearly marked on each bin.
Vibrations
- You may feel slight vibrations from the construction work.
Replacing and Taking Care of Your Sod
- The contractor will take care of any sod we replace for 30 days.
- You can help the sod to stay healthy by watering it for one hour in the early morning, two or three times a week. This is especially important in hot or dry weather.
- We will replace your sod as soon as we can, but there may be a short delay.
- It is very common for the work area to settle a bit following construction. If you notice any settlement, please let the project manager or inspector know and we will ensure the contractor fixes it.
Repairing Your Driveway
- If we need to cut your driveway to replace the existing service valve or access the watermain, we will repair the asphalt in the disturbed area. As all of the streets effected by watermain replacement in this project are scheduled for City of Mississauga road resurfacing in 2021, the repair across your driveway from edge to edge will be conducted then. Unfortunately, the Region or the City cannot completely replace your driveway.
- If you have any concerns, please call the Project Manager.
- We will repair your driveway as soon as we can, but there may be a short delay.
- If you are planning to have your driveway paved, you are encouraged to wait until the City of Mississauga’s road resurfacing program commences in order to avoid any cuts or patches that may be required on your driveway during the work.
Repairing the Road, Curbs, and Sidewalks
- We will start restoring the road and boulevard once all replacements and service transfers are complete and as weather permits.
- Our contractor will pave only the trench they dug and install temporary curbs because the City of Mississauga plans to pave Paisley Boulevard West, Consulate Road, and President Boulevard in 2021. The easement pathways will be restored to their existing condition.
Project Updates
- The Region of Peel will always let you know if there are any major changes to the plans.
- We will try to disturb you as little as possible.
- Please call the project manager or inspector if you have any concerns or special needs.
How Did We Do?
- After we’ve finished, we will give you a postage-paid card for you to rate our work.
- Please complete the card and mail it back to us.