Public notice

Erin Mills Parkway Corridor Improvements Between Credit Valley Road and Britannia Road, City of Mississauga

Where the work is happening

On Erin Mills Parkway from Credit Valley Road to Britannia Road in the City of Mississauga. View resident sketch.

What we are doing

The work includes:

When

We expect to start work in spring 2021 and finish in fall 2021.

Working Hours

Typical hours of work are from 7 a.m. to 7 p.m., Monday to Friday.

Some weekend and overnight work will be required to mitigate impact to traffic for certain operations like asphalt paving.

Extended working hours may cause some inconvenience however they will help facilitate completion of the project as quickly and safely as possible.

Traffic Impacts

The project will be phased to minimize traffic disruption while maintaining a safe working environment as required under the Occupational Health and Safety Act.

Two lanes of traffic in either direction will be maintained for most works, with short duration single lane reductions only occurring during off-peak traffic hours for select activities.

Emergency access will be maintained at all times.

Please use caution when travelling through the work zone.

Public Transit

Mississauga Transit stops may be temporarily relocated when work occurs nearby.

Please follow posted signs to the nearest alternative or relocated stop location.

Driveway Access

We will maintain driveway access as much as possible and if we need to block your driveway for a short time you will be contacted to arrange for the best time

We will make sure businesses have access at all times.

Project Updates

The Region of Peel will always let you know if there are any major changes to the plans. We will try to disturb you as little as possible.

Construction project updates can also be found at peelregion.ca/construction

Who you can call

Region of Peel
Contact Person Responsibilities Telephone Number
Olek Garbos
Stephen Yirenkyi
Project Manager
Regional Inspector
905-791-7800 ext. 7429
905-791-7800, ext.3246
Four Seasons Site Development Ltd
Four Seasons Site Development Ltd will do the work, under contract to Region of Peel
Nick Marrone
Nermeen Hegazy
James Vernon
Project Manager
Project Co-ordinator
Health & safety Co-ordinator
416-522-6175
416-676-6960
416-528-4003
Wood PLC
Wood PLC will manage and oversee the work, under contract to Region of Peel
Jason Stahl
Mohammed Abdul
Project Manager
Contract Administrator
905-335-2353 ext. 3045
289-962-4940