Frozen water service replacements and improvements
3174 Cantelon Crescent, 5644 Ninth Line and 5476 Ninth Line. Project 21-1310 K
What are we doing
- Replacing and relocating the existing 25mm water service pipes at 3174 Cantelon Crescent, 5644 Ninth Line and 5476 Ninth Line.
Why?
- To keep the water services from freezing over the future winter months.
When?
- We expect to start work on or about Monday November 8th starting at 3174 Cantelon Crescent, followed by the replacements on Ninth line.
- The project should be completed by November 19th, 2021. All work is under warranty for two years from the completion date.
- We will start restoring the road when all water system replacements and transfers are complete, and as weather permits.
Who can you call?
Region of Peel | ||
Contact Person | Responsibilities | Telephone Number |
---|---|---|
Mark Ferreira | Project Manager | 905-791-7800, ext. 5119 |
Gus Afuwape | Inspector | 905-791-7800, ext. 3246 |
GIO Contracting Gio Contracting will do the work, under contract to the Region of Peel |
||
Leo Giovannelli | Project Manager | 647-822-3259 |
Working hours
- Our contractor’s normal working hours are from 7 a.m. to 7 p.m. These hours are consistent with the local municipality’s bylaws. We understand this may cause some inconvenience, but a shorter working day would mean the project would take longer to complete.
Traffic and parking control
- We may need to reduce traffic to a single lane during construction.
- If we have to reroute traffic, we will place signs giving directions.
Driveway access
- Due to construction activities, we may need to block your driveway for a short time. We will contact you before we do this to arrange for the best time and for alternate access, if needed. If your driveway is blocked, you may choose to park on a side street for a short time. If you need immediate access to your driveway, the contractor will have road plates available to quickly allow access in and out of your driveway.
- Please call the Project Manager if you have special needs related to access or business hours.
Irrigation or sprinkler systems
- Please tell the inspector if you have underground irrigation or a sprinkler system outside your property line.
- You may wish to move the sprinkler lines to inside your private property to avoid damage.
Trimming trees
- If tree branches within the right-of-way interfere with construction, the contractor will have the trees pruned before equipment enters the drip line of the tree.
- If tree branches on private property interfere with construction, they will be pruned back to the nearest suitable trunk, crotch or branch.
- The contractor will ask you for permission before cutting any branches on private property. If you do not allow the contractor onto your property to trim the branches, the branches will be cut vertically at the property line.
Interrupting your water supply
- It is our goal to let you know 48 hours (2 days) in advance if we need to shut off your water. Occasionally, we may have to reduce this notice to 24 hours.
- For water interruption during service transfers, the contractor will notify you the day of the transfer as this will be a brief interruption. This will ensure proper notification for short duration works.
- If we have to shut off your water because of an emergency, we will do everything we can to fix the problem as quickly as possible.
Waste collection
- Your garbage, recycling and organics containers will continue to be picked up on your regularly scheduled day. It is the contractor’s responsibility to move your garbage, recycling and organics bins to a location where our collection vehicles can pick them up. Empty containers will be returned to their corresponding addresses. Please make sure your house number is clearly marked on each bin.
Vibrations
- You may feel slight vibrations from the construction work.
Replacing and taking care of your sod
- The contractor will take care of any sod we replace for 30 days.
- You can help the sod to stay healthy by watering it for one hour in the early morning, two or three times a week. This is especially important in hot or dry weather.
- We will replace your sod as soon as we can, but there may be a short delay.
- It is very common for the work area to settle a bit following construction. If you notice any settlement, please let the project manager or inspector know and we will ensure the contractor fixes it.
Repairing your driveway
- If we need to cut your driveway to replace the existing service valve or access the watermain, we will repair the asphalt in the disturbed area from edge to edge across the driveway. Unfortunately, the Region cannot completely replace your driveway.
- Before the driveway restoration work, we will send you an update with contact information for the contractor, in case you wish to have the remainder of your driveway (private side) paved at the same time.
- If you have any concerns, please call the Project Manager.
- We will repair your driveway as soon as we can, but there may be a short delay.
Repairing the road, curbs, and sidewalks
- We will start restoring the road and boulevard once all replacements and service transfers are complete and as weather permits.
- We will complete the restoration on a street-by-street basis.
Private-side servicing
- We will replace the water service pipe to your service box (the round valve near the property line).
- As the pipe between the service box and the building is probably the same age and condition as the watermain, you may wish to replace it to ensure a constant supply of high-quality drinking water to your tap. This is the property owner’s responsibility; the Region cannot do this work for you.
- For more information on replacing the private-side water service, please visit peelregion.ca/pw/water/private-side-water-service.htm
Project updates
- The Region of Peel will always let you know if there are any major changes to the plans.
- We will try to disturb you as little as possible.
- Please call the project manager or inspector if you have any concerns or special needs.
Construction statement regarding COVID-19
Critical infrastructure construction is an essential service. We’re keeping employees, contractors and the community safe by complying with provincial guidelines, physical distancing, using personal protective equipment, and adjusting work schedules and shifts.