Sanitary sewer replacement and improvement

Minotola Avenue, Justine Drive. Project 21-2300C

June 30, 2022 update

The Region of Peel will be working in your neighborhood to replace the sanitary sewers and maintenance holes (commonly referred to as manholes). This work will take place along Minotola Avenue and Justine Drive. Sanitary sewers are underground pipes that carry wastewater from your home to a wastewater treatment plant. Wastewater is created when water goes down the drain or is flushed down the toilet. As pipes age and our population grows, we need to replace older sewers to keep providing you with high quality wastewater services.

Construction schedule

This construction work will be completed on a street-by-street basis. Construction on Minotola Avenue is expected to begin in late July 2022 followed by the construction on Justine Drive. The entire project should be completed by late 2022.

All work is under warranty for two years from the completion date.

Contractor and working hours

The work will be completed by Rymall Construction Inc. under contract to the Region of Peel. This contractor’s normal working hours are from 7 a.m. to 7 p.m., Monday to Friday. These hours are consistent with the local municipality’s bylaws. We understand this may cause some inconvenience, but shorter working days would require your neighbourhood to be under construction for a longer period of time.

Traffic and parking

This work will be phased to minimise traffic disruptions in the area. We may need to temporarily close roads or reduce traffic to a single lane during construction. If we must reroute traffic, we will place signs giving directions. On-street parking will be reduced during construction when we are actively working on your street.

Interrupting your water supply

It is our goal to let you know 48 hours (2 days) in advance if we plan to shut off your water for an extended period (several hours). Occasionally we may have to reduce this notice to 24 hours. If we need to shut off your water for a short duration (less than one hour), we will knock on your door to notify you. If we must shut off your water due to an emergency, we will knock on your door to alert you, and do everything we can to fix the problem as quickly as possible.

Areas impacted by construction

Replacing sanitary sewers usually requires digging a trench within the municipal right-of-way, the land owned by the municipality between the water service box and the street. (The water service box is a small, round, metal valve located outside, on the property line between your house and the road.) Depending on the location of the sanitary sewer, this trench might cause temporary damage to roads, curbs, sidewalks, boulevards, driveway aprons, and lawns within the municipal right-of-way.

In addition, depending on its condition, the Region of Peel may also repair or replace the municipal portion of the sanitary sewer connection, the smaller underground pipe running from your home to the Regional sanitary sewer system. This may require digging up either the lawn or driveway above this section of pipe and disturbing an area at least 2 square meters. Any damage caused by Regional construction will be repaired.

We recommend you delay any driveway paving or major landscaping projects until this construction work is completed.

In-ground sprinkler systems

As your front lawn may be affected by this construction work, we strongly recommend moving any sprinkler lines that are located in the municipal right-of-way or next to the sidewalk. If you can’t relocate these sprinkler lines, please send us a map created by your irrigation contractor or flag each sprinkler head that is located within one meter of the sidewalk, curb, or driveway. This will allow us to minimize the impact to your sprinkler system.

Tree trimming

If tree branches within the municipal right-of-way interfere with construction, the trees will be pruned beforehand. If tree branches on private property interfere with construction, they will be pruned back to the nearest suitable trunk or branch. If you do not allow personnel onto your property to trim the tree, the branches will be cut vertically at the property line.

Repairing areas impacted by construction

We will start repairing the road, curb, sidewalk, driveways, and lawns once the new sanitary sewer is buried, and work has been completed on all sanitary sewer connections on your street. Repairs may be delayed due to contractor availability or certain seasonal weather conditions.

For example:

Repairing grassy areas

The contractor will replace any damaged sod (grass) on the boulevard or your front lawn and will take care of the new sod for 30 days. You can help the sod stay healthy by watering it. A longer ‘deep root watering’ works better to establish new sod than watering more frequently for a shorter time. Watering in the early morning allows more water to soak in instead of evaporating.

Repairing driveways

Temporary restoration

The City of Mississauga is planning to complete roadwork on some streets in your neighborhood within the next few years. Where this roadwork will also impact driveways, curbs, sidewalks, and lawns next to the sidewalk, we will:

The Region of Peel’s repairs are temporary, as the City of Mississauga will complete restoration as part of their roadwork. The City of Mississauga will send you a separate notice about this additional construction.

For streets where roadwork is not planned by the City of Mississauga, repairs will be done by the contractor after the sanitary sewer construction work is completed, depending on contractor availability and seasonal weather.

Driveway access

It may be necessary to block your driveway for a short time when crews are digging the trench for the sanitary sewer, working on your sanitary sewer connection, or completing other construction activities. If so, we will knock on your door to notify you. If a trench prevents access to your driveway, the contractor will have metal road plates available to allow access if required. We will make sure businesses always have access. Please contact us if you have special needs related to access.

Waste collection

If you receive waste collection from the Region of Peel, your garbage, recycling and organics containers will continue to be picked up on your regularly scheduled day. It is the contractor’s responsibility to move your garbage, recycling, and organics bins from the end of your driveway to a location where waste collection vehicles can pick them up. Empty containers will be returned to their corresponding addresses. Please make sure your house number is clearly marked on each bin. This helps us return empty bins to the correct address.

Vibrations

You could feel slight vibrations from the construction work.

Optional protection plans for your exterior water pipes, wastewater pipes, and in-home plumbing

Many homeowners are not aware that they are responsible for maintaining the water and wastewater pipes both inside their home and outdoors up to the property line. If one of these pipes breaks, it can cause unexpected and costly repairs. The Region of Peel has partnered with Service Line Warranties of Canada (SLWC) to offer homeowners optional, affordable protection from unexpected home repairs. Learn more about the protection plans at plansforpeel.ca.

Safety during construction

Construction zones require extra caution to keep everyone safe – pedestrians, cyclists, drivers, and construction workers. When driving, walking, or biking through the construction area, please be aware of your surroundings, watch for construction crews and other road users, slow down, account for delays, and consider other routes if possible. Learn more about how to stay safe in construction zones.

We value your feedback

After we’ve finished, we will invite you to provide feedback on the construction project.

Thank you for your patience as we complete this necessary work. This work will allow us to continue providing you with high quality wastewater services. If you have any questions, please contact us.