Watermain replacement and improvement

Bloor Street between Havenwood Drive & Bridgewood Drive. Project 22-1310 D

Peel Region will be working in your area to replace the watermain(s) along Bloor Street (Between Havenwood Drive and Bridgewood Drive), as shown on the attached map. Watermains are underground pipes that bring tap water from our water treatment plants to your area. As pipes age and our population grows, we need to replace older watermains to keep providing high quality water to you.

Construction schedule

Construction is planned to begin June 2023 and be completed in the end of 2023. These timelines are estimates, as weather and other unexpected events may impact our timelines.

All work is under warranty for two years from the completion date.

Sign up for email notices

Receive timely project updates right to your inbox by signing up for e-notices at peelregion.ca/construction/signup.

Contractor and working hours

The work will be completed by New Alliance Ltd and supported by EXP Services Inc, both under contract to the Region of Peel. This contractor’s normal working hours are from 7 a.m. to 7 p.m., Monday to Friday. These hours are consistent with the local municipality’s bylaws. We understand this may cause some inconvenience, but shorter working days would require your area to be under construction for a longer period of time.

Traffic and parking

We may need to temporarily close roads or reduce traffic to a single lane during construction. If we must reroute traffic, we will place signs giving directions. On-street parking will be reduced during construction when we are actively working on your street.

Interrupting your water supply

We anticipate that this construction project will require temporarily shutting off your water.

If we must shut off your water due to an emergency, we will knock on your door to alert you, and do everything we can to fix the problem as quickly as possible.

Areas impacted by construction

Installing watermains usually requires digging a trench within the municipal right-of-way, which includes the street and the land owned by the municipality between the water service box and the street. (The water service box is a small, round, metal valve located outside, on the property line between your home or business and the road.) Depending on the location of the watermain, this trench might cause temporary damage to roads, curbs, sidewalks, boulevards, driveway aprons, and lawns within the municipal right-of-way.

To maintain your water supply, the Peel Region will also replace:

This requires digging up your water service box located in the lawn or driveway, and disturbing an area at least two square meters.

Any damage caused by Peel Region’s construction will be repaired.

We recommend that you delay any driveway paving or major landscaping projects until this construction work is completed.

In-ground sprinkler systems

As the front lawn may be affected by this construction work, if you have an in-ground sprinkler system we strongly recommend moving any sprinkler lines that are located in the municipal right-of-way or next to the sidewalk. If you can’t relocate these sprinkler lines, please send us a map created by your irrigation contractor or flag each sprinkler head that is located within one meter of the sidewalk, curb, or driveway. This will allow us to minimize the impact to your sprinkler system.

Tree protection and trimming

Trees located in the municipal right-of-way will be protected during construction using temporary fencing. If tree branches within the municipal right-of-way interfere with construction, the trees will be pruned beforehand.

If tree branches on private property interfere with construction, they will be pruned back to the nearest suitable trunk or branch. The contractor will contact you before any pruning of private trees occurs. If you do not allow personnel onto your property to trim the tree, the branches will be cut vertically at the property line.

Repairing areas impacted by construction

We will start repairing the road, curb, sidewalk, driveways, and lawns once the new watermain is buried and new water service pipes have been connected to all properties on your street. Repairs may be delayed due to contractor availability or certain seasonal weather conditions.

For example:

Repairing grassy areas

The contractor will replace any damaged sod (grass) on the boulevard or your front lawn and will take care of the new sod for 30 days. You can help the sod stay healthy by watering it. A longer ‘deep root watering’ works better to establish new sod than watering more frequently for a shorter time. Watering in the early morning allows more water to soak in instead of evaporating.

Temporary restoration

The City of Mississauga is planning to complete roadwork on your street within the next few years. As this roadwork may also impact driveways, curbs, sidewalks, and lawns next to the sidewalk, we will:

The Region of Peel’s repairs are temporary, as the city of Mississauga will complete restoration as part of their roadwork. The city of Mississauga will send you a separate notice about this additional construction.

Driveway access

It may be necessary to block your driveway for a short time when crews are digging the trench for the watermain, replacing your water service box and pipe, or completing other construction activities. If so, we will knock on your door to notify you. If a trench prevents access to your driveway, the contractor will have metal road plates available to allow access if required. Whenever possible, we will work to ensure businesses can be accessed.

Please contact us if you have special needs related to access.

Waste collection

If you receive waste collection from the Region of Peel, your garbage, recycling, and organics will continue to be picked up on your regularly scheduled day. It is the contractor’s responsibility to move your garbage, recycling, and organics bins from the end of your driveway to a location where waste collection vehicles can pick them up. Empty containers will be returned to their corresponding addresses. Please make sure your house number is clearly marked on each bin. This helps us return empty bins to the correct address.

Vibrations

You could feel slight vibrations from the construction work.

Safety during construction

Construction zones require extra caution to keep everyone safe – pedestrians, cyclists, drivers, and construction workers. When driving, walking, or biking through the construction area, please be aware of your surroundings, watch for construction crews and other road users, slow down, account for delays, and consider other routes if possible. To learn more about how to stay safe in construction zones, visit peelregion.ca/workzonesafety.

Keeping you informed

We will let you know if there are any major changes to the plans.

We value your feedback

After we have finished, we will invite you to provide feedback on the construction project. You can sign up to receive this survey electronically at peelregion.ca/construction/signup.

Thank you for your patience as we complete this necessary work. This work will allow us to continue providing you with high quality tap water. If you have any questions, please contact us.

Water Linear Engineering
Engineering Services Division
Public Works, Region of Peel
Email: construction@peelregion.ca
Phone: 905-791-7800 ext. 4409