Public Works Construction

Construction in Peel: Brampton

Queen Street West Widening and Reconstruction from 300m East Of Mississauga Road to Chinguacousy Road City of Brampton
Project #05-4045

What are we doing?

  • This Contract is for the reconstruction and widening of Queen Street West. The work includes, but is not limited to:
    • Excavation
    • Storm sewer system installation & Low Impact Development (LID) measures
    • Five (5) culvert replacements with new structures
    • Sidewalks and bus stop platforms & multi-use-trail
    • ZUM transit facilities
    • Temporary and permanent traffic control signals
    • Hot mix paving
    • Placement of pavement markings & traffic signage

Where?

When?

  • Start: July 11 2016.
  • Finish: November 2018, weather permitting.

Who can you call?

Drainstar Contracting Limited under contract to the Region of Peel
Contact Person Responsibilities Telephone Number
Mike Sriskantha Project Manager 416 990 0117
Tony Cota Superintendent 416 990 7780
Region of Peel
Contact Person Responsibilities Telephone Number
Barry Mulcahy Project Manager 905-791-7800 ext. 7914
Joe Ierullo Regional Inspector 647-956-9174
Garry Padda Regional Inspector 905-791-7800 ext. 3246

Working Hours

  • Our contractor's normal working hours are from 7.00 a.m. to 6.00 p.m.
  • Some paving works will be done at night from 7.00 p.m. to 5.30 a.m.
  • These hours are consistent with the local municipality's bylaws. We understand this may cause some inconvenience, but a shorter working day would mean the project would take longer to complete.

Traffic Control

  • Temporary lane closures will be required during non-peak hours.
  • We will need to reduce traffic to a single lane (each direction) and temporarily block intersections during construction.
  • Peel Regional Police will be present on occasion to direct traffic safely.
  • Emergency access will be maintained at all times.
  • Barriers and signs will be placed for safety and direction, as required under the Occupational Health and Safety Act.

Driveway Access

  • We anticipate that driveway access will be maintained in so far as possible.
  • If we need to block your driveway for a short time you will be contacted to arrange for the best time and for alternate access. If your driveway is blocked, you may choose to park on a side street for a short time.
  • We will make sure businesses have access at all times.
  • Please call the Project Manager if you have special needs related to access.

Project Updates

  • The Region of Peel will keep you informed of any substantial changes in the project scope or schedule.
  • We are committed to ensuring minimum disruption to your homes and businesses.
  • Please call the project manager or inspector if you have any special needs.

Email questions or comments

Back to Brampton Construction Projects

Revised: Thursday November 23 2017

www.peelregion.ca

Home | Contact Us | Search | A-Z Topic List
Privacy & Terms of Use | Service Commitment

Smaller Text Larger Text