Road maintenance Service Levels

O. Reg 239/02 Minimum Maintenance Standards for Municipal Highways
Category Asset or Activity Minimum Maintenance Standard (MMS) Peel Enhancement to MMS
Winter Maintenance Road surface and atmospheric weather monitoring
  • Once per shift or 3 times or per calendar day.  24 hours preceding an alleged formation of ice or accumulation of snow.
4 times per calendar day
Winter Maintenance Roadway and road right-of-way patrol
  • October 1st to April 30th:  3 times every 7 days, unless there is a probability of snow accumulation on roadways, ice formation on roadways or icy roadways, in which case it is performed at intervals deemed necessary by the municipality to check for such conditions.
Once per 24 hours/7 days per week, November to April
Winter Maintenance

Roadway snow & ice formation and accumulation anti-icing, spreading & plowing

  • Accumulation greater than or equal to 2.5 cm
  • After snow accumulation has ended, bring back to 2.5 cm or less within 4 hours.
Maintain as bare as possible throughout snow event.  After snow accumulation has ended, bring to bare conditions within 4 hours.
Winter Maintenance Roadway designated bicycle lane
  • Accumulation greater than or equal to 2.5 cm
  • After snow accumulation has ended, bring back to 2.5 cm or less within 8 hours.
N/A
Winter Maintenance Sidewalks
  • Accumulation greater than or equal to 8 cm
  • After snow accumulation has ended, reduce the snow to a depth less than or equal to 8 cm within 48 hours.
N/A
Roadway Maintenance Roadway and road right-of-way summer patrol
  • 3 times every 7 days
4 times every 7 days
Roadway Maintenance Atmospheric weather monitoring
  • Monitor current and forecast occurring in next 24 hours, once per calendar day.
  • Increase monitoring if probability of extreme weather conditions are approaching.

Monitor current and forecast twice per calendar day

Roadway Maintenance

Potholes, paved road surface

  • If hole exceeds both 600 cm2 surface area and 8cm depth, repair within 4 days after becoming aware of the condition
N/A
Roadway Maintenance

Potholes, Paved or Non paved Surface of Shoulder

  • If hole exceeds both 1500 cm2 surface area & 8 cm depth, repair within 7 days after becoming aware of the condition.
N/A
Roadway Maintenance Shoulder drop off
  • If hole exceeds both 1500 cm2 surface area & 8 cm depth, repair within 7 days after becoming aware of the condition
  • If deeper than both 8 cm for 20 metres, repair within 4 days after becoming aware of the condition.

Resurfacing/adding granular: Completed annually in construction season

 2 continuous grading cycles/year
Roadway Maintenance Debris and Litter pick up
  • Remove roadway debris as soon as practical after becoming aware of the condition.
All roadways once in spring and before each grass cutting
Roadway Maintenance Paved roadway surface cracks
  • If greater than 5 cm wide and 5 cm deep for distance of 3 metres or more, repair within 30 days.
N/A
Roadway Maintenance Roadway surface discontinuities
  • If discontinuity exceeds the height of 5 cm, repair within 2 days after becoming aware of the condition.
N/A
Bridge Deck Maintenance Surface discontinuities
  • If discontinuity exceeds the height of 5 cm, repair to as soon as practical after becoming aware of the condition
N/A
Bridge Deck Maintenance Surface area spalls
  • If spall exceeds both 600 cm2 surface area and 8 cm depth, repair within 4 days after becoming aware of the condition
N/A
Sidewalk Maintenance Surface discontinuities
  • If discontinuity exceeds 2 cm – treat as soon as practical after becoming aware of the condition.
  • Inspect once per calendar year, taking place not more than 16 months from the previous inspection.
N/A
Sign Maintenance Level One regulatory signs (such as ‘stop’, ‘yield’ or ‘one way’ signs)        
  • If the sign is illegible, improperly oriented, obscured or missing, it must be repaired or replaced as soon as practical after becoming aware of the condition
N/A
Sign Maintenance All other regulatory and warning signs
  • If the sign is illegible, improperly oriented, obscured or missing, repair or replace within 7 days.
N/A
Sign Maintenance Retro-reflectivity inspection
  • Inspect once per year, with each inspection taking place not more than 16 months from the previous inspection.
N/A
Luminaires Streetlights
  •  Inspect once per year, with each inspection taking place not more than 16 months from the previous inspection.
  • For 3 or more consecutive failures on same side of highway and/or 30% failures of high mast in any KM of highway, repair is to be completed within a7 days becoming aware of the condition
N/A
Traffic Control Signal system
  • Repair or replace defective component as soon as practical after becoming aware of the defect.
N/A

 

Peel Region Road Maintenance – Additional Service Levels
Category Asset or Activity Minimum Maintenance Standard (MMS)
Winter Maintenance Snow clearing
  • After plow operations are complete, remove snow posing hazard/risk to travelled portion of roadway as soon as practical after becoming aware of condition.  For example, clearing snow and ice from ditches, culverts, manholes, catch basins, guiderails and bridge ends.  Install plow markers annually in the fall.
Winter Maintenance Snow removal
  • Roadway – remove hazards as soon as practical post event.
  • Sight line – remove obstructions as soon as practical post event.
  • Pedestrian safety-  remove obstructions as soon as practical post event at  high pedestrian traffic passages
  • Structures - if storage is limited, remove accumulated snow ahead of the next storm or as soon as practical post event.
  • Underpass - if storage is limited, remove accumulated snow ahead of the next storm or as soon as practical post event.
  • Roadside windrows - where roadside storage is limited, remove accumulated snow ahead of the next storm or as soon as practical post event.
Winter Maintenance Winter material stock piling
  • Winter materials stocked in November and maintained no less than 50% during winter season. 
  • Salt supply shall be coordinated such that stockpiling remains continuous through winter season, as dictated by weather.
Winter Maintenance Snow fence install and removals
  • Install fences at predefined locations on private property in October/November to prevent blowing snow across roadways.
  • Repair downed fence within 7 days after becoming aware of condition.
  • Remove fences in April/May.  Purchase of corn rows prior to annual corn harvest for natural snow fence program.
Winter Maintenance Spring sweeping- clean up
  • 1 cycle per season, completed annually  at the end of winter maintenance: 1 cycle per season. 
  • Material swept to the road surface for pick up shall remain on no longer than 48 hours and shall not constitute a hazard to the road users.
Roadway Maintenance Maintenance hole repair
  • Hazards responded to immediately, marked and temporarily fixed within 24 hours after becoming aware of condition. 
  • Non-hazardous repairs completed within 90 days of notice.
Roadway Maintenance

Curb and gutter repair

  • Inspected annually and scheduled for repair based on priority ranking:
    >50 mm settlement is replaced. 
    70%-100% damage and 3 metres long, shall be scheduled for repair.
  • Hazards responded to, marked, and temporarily fixed within 24 hours after becoming aware of condition. 
  • Permanent repairs to be scheduled in the construction season. 
Roadway Maintenance Summer sweeping
  • South district roadways- 2 Passes during summer months.
  • North district hamlets and rural intersections, bike routes/paved shoulders - 6 passes during summer months.
  • Emergency street sweeping, to eliminate localized hazards to vehicular traffic - with a one-hour response time throughout the year, weather permitting.
Roadway Maintenance

Pavement marking retrace (Line painting)

  • Retraced once, annually.
  • Pavement markings removed due to construction or maintenance activities will be reinstated within 48 hours of completion of construction/ maintenance activity, weather permitting.
Bridge Deck Maintenance Annual Inspection
  • Wash bridge deck and visual inspection annually.
  • Engineering inspection every 2 years
Bridge Deck Maintenance Graffiti removal
  • Removed within 30 days after becoming aware, unless of a sensitive nature which will be removed as soon as practical.
Roadway Maintenance Urban mowing
  • 12 cuts per season starting in May.
  • Areas that could pose risk to the travelling public to be cut within 7 days (for example, vegetation interfering with sight lines)
Roadway Maintenance Rural mowing
  • Twice per year - summer months 1st cut mid-July, 2nd cut by end of September.
  • Areas that could pose risk to the travelling public to be cut within 7 days (for example, vegetation interfering with sight lines)
Roadway Maintenance Debris and Litter pick up
  • Once in the spring and ahead of grass cutting activity
  • Deploy resources, as soon as practical after becoming aware of condition
Roadway Maintenance Tree removal & brush cutting
  • Hazards or risk to public safety are responded to within 24 hours after becoming aware of conditions with full clean up achieved within 7 days.
  • Non-hazardous brush or trees scheduled for removal in priority order.
Roadway Maintenance Weed control
  • Based on findings and responded to by Certified Weed Control Inspector.
Roadway Maintenance

Paved splash strip

  • Permanent repairs completed in summer months.
  • Temporary stabilization within 24 hours after becoming aware of the condition
Roadway Maintenance Routine shoulder grading
  • Regrading - 2 cycles per year - spring and fall.
Roadway Maintenance Shoulder washout
  • Hazards temporarily stabilized in 24 hours after becoming aware of condition and permanent repairs in 60 days.
  • Non-hazards completed within 90 days after identified
Roadway Maintenance Sound barrier
  • Detailed Condition Assessment inspection completed every 2 years (spring)
  • Damage stabilized in 24 hours after becoming aware of condition; scheduled repair within 90 days after identified.
  • Graffiti removal within 30 days after becoming aware of condition, unless of sensitive nature in which case, it will be dealt with as soon as practical.
Roadway Maintenance Mailbox repair
  • Temporary mailbox installed within 48 hours after becoming aware of damage.  Permanent repair of post and standard mailbox within 30 days between April and November.
Storm Maintenance Safety Barrier
  • Hazards marked and temporary repairs completed within 24 hours after becoming aware  of condition. Scheduled repair within 90 days, based on priority ranking, during construction season.
  • Flooding of 5 cm+ standing water respond immediately after identified..
  • 1/3 of the system is cleaned once per year in the fall.
Storm Maintenance Road culvert
  • Respond to deficiencies within 7 days after becoming aware of condition
  • Maintain sediment buildup at less than 25%.
  • Flooding or 5 cm+ standing water, deploy resources as soon as practical after identified.
  • Culverts patrolled during significant rain events, and before and after spring freshet.
  • Blockages will be removed as soon as practical.
Storm Maintenance Ditching
  • Immediate response to emergency service requests for flooding.  Stabilized in 24 hours after becoming aware of condition; permanent repairs done in 90 days.
  • Obstructions and slope erosion shall be addressed as soon as practical.