Public Works Construction

Construction in Peel: Brampton

Widening and Reconstruction of the Gore Road
from North of Castlemore Road to North of Squire Ellis Drive
Project # 07-4030

What are we doing?

  • Widening from 2 to 4 lanes, and reconstructing of the Gore Road.
  • Widening and improving the Gore Road and Countryside Drive intersection.
  • Widening Humber River Bridge.

To complete all the above we will:

  • Remove existing culverts and install new ones.
  • Remove existing and install new asphalt pavement.
  • Install new storm sewer and create new ditches.
  • Install new street lights, traffic signals and signs.
  • Construct concrete curbs and sidewalks.
  • Install new landscaping in vicinity of Humber River Bridge.

View area map (PDF).

Where?

  • Approximately 400m north of Castlemore Road to 200m north of Squire Ellis Drive.

When?

  • Start: mid–July 2017
  • Finish: November 2019

Who can you call?

  • The work will be performed by Rafat General Contractor Inc. with Contract Administration services provided by IBI Group on behalf of the Region of Peel. The contact names and telephone numbers are listed below:
Region of Peel
Contact Person Responsibilities Telephone Numbers
John Hasselbacher Project Manager (905) 791-7800 x7912
Ommar Moeen Inspector (647) 643-3627
Rafat General Contractor Inc.
under contract to the Region of Peel
Contact Person Responsibilities Telephone Number
Laith Azzo Project Manager (416) 771-6184
Maan Sarsam Site Superintendent (416) 276-1891
IBI Group
under contract to the Region of Peel
Contact Person Responsibilities Telephone Number
Elizabeth Kadela Project Manager (416) 526-6996
Derek Gretka Contract Administrator (416) 704-3225

Working Hours

  • Our contractor’s normal working hours are from 7 a.m. to 7 p.m.
  • These hours are consistent with the local municipalities’ by-laws. We understand this may cause some inconvenience, but a shorter working day would mean the project would take longer to complete.

Traffic and Parking Control

  • Temporary lane closures will be required during non-peak hours.
  • Emergency access will be maintained at all times.
  • Barriers and signs will be placed for safety and direction, as required under the Occupational Health and Safety Act.
  • Note that speed limit along The Gore Road will be reduced for the project duration.

Driveway Access

  • We anticipate that driveway access will be maintained in so far as possible.
  • If we need to block your driveway for a short time you will be contacted to arrange for the best time and for alternate access. If your driveway is blocked, you may choose to park on a side street for a short time.
  • We will make sure businesses have access at all times.
  • Address tabs and mail boxes will be temporary relocated and reinstated at the completion of work.
  • Please call the Project Manager if you have special needs related to access or business hours.

Project Updates

  • The Region of Peel will keep you informed of any substantial changes in the project scope or schedule.
  • We are committed to ensuring minimum disruption to your homes and businesses.
  • Please call the project manager or inspector if you have any special needs.

Email questions or comments

| Back to Brampton Construction Projects |

Revised: Friday July 28 2017