Watermain replacement
Mississauga Road, Beaufort Terrace and Eckland Court. Project 18-1310A.
Update
- The new watermains on Mississauga Road, Beaufort Terrace, and Eckland Court have now been installed. The next phase is to commission the watermain and put it into service. Properties on these streets will now have their individual water lines transferred from the old watermains to the new watermains.
- A new water service line will be brought up to the property line where a new water service box will also be installed. Where possible your water line will be brought up to the property line using trenchless methods. However, the area around the water service box will be excavated.
When?
- We expect to start work on or around May 19, 2021, starting on Mississauga Road.
- The project should be completed before November 2021. All work is under warranty for two years from the completion date.
- We will start restoring the road when all water system replacements and transfers are complete, and as weather permits.
Who you can call
Region of Peel | ||
Contact Person | Responsibilities | Telephone Number |
---|---|---|
Rene Gomez | Project Manager | 905-791-7800, ext. 3809 |
Stan Domanski | Inspector | 905-791-7800, ext. 3246 |
Four Seasons SiteDevelopment Four Seasons Site Development will do the work, under contract to the Region of Peel |
||
Sanjay Bansal | Project Manager | 1-905-789-0111 |
Flemming Stidsen | Site Superintendent | 1-905-789-0111 |
Working hours
- Our contractor’s normal working hours are from 7 a.m. to 7 p.m. These hours are consistent with the local municipality’s bylaws. We understand this may cause some inconvenience, but a shorter working day would mean the project would take longer to complete.
Interrupting your water supply
- It is our goal to let you know 48 hours (2 days) in advance if we plan to shut off your water for an extended period (several hours). Occasionally, we may have to reduce this notice to 24 hours.
- On the day we connect your water service to the new watermain, the contractor will let you know that your water will be shut off for a brief period. This will ensure proper notification for short duration works.
- If we must shut off your water because of an emergency, we will do everything we can to fix the problem as quickly as possible.
Project updates
- The Region of Peel will always let you know if there are any major changes to the plans.
- We will try to disturb you as little as possible.
- Please call the project manager or inspector if you have any concerns or special needs.
How did we do?
- After we’ve finished, we will give you a postage-paid card for you to rate our work.
- Please complete the card and mail it back to us.