Watermain and sanitary sewer replacement and improvement

Queen Street East from Goreway Drive to Cherrycrest Drive. Project 18-1169

Peel Region has been working in your neighbourhood to install watermains and sanitary forcemains along Queen Street East. This work is required to maintain and improve existing water and wastewater services.

At this stage in the project, lane reductions will be required to complete this work.

Traffic impacts

  • Eastbound Queen Street East will be reduced to two lanes from east of Goreway Street to west of McVean Drive. This lane reductions are expected to occur from Thursday September 28 to Friday November 3rd.
  • The ZUM bus stops in this vicinity will not be affected:
    • Goreway – Queen Station Stop Eastbound
    • McVean – Queen Station Stop Eastbound
  • Westbound Queen Street East will continue to be reduced to two lanes from west of McVean Drive to east of Goreway/Humber Station Road. This lane reductions will continue through to the spring of 2024.
  • The ZUM bus stop in this vicinity will not be affected:
    • McVean – Queen Station Stop Westbound
  • Two lanes of traffic in each direction will be provided at all times, unless notified otherwise.
  • Different portions of the work will have additional traffic impacts, and those will be communicated in advance including the details of the lane restrictions.
  • PVMS boards will continue in place throughout the works and will be updated accordingly.

Please expect delays and choose alternate routes if possible.

We apologize for any delays or inconvenience resulting from these traffic impacts.

Keeping you informed

Weather and other unpredictable events may change the date of these traffic impacts. Receive timely project updates right to your inbox by signing up for e-notices.

Follow Peel Public Works on Twitter for project updates.

Information on this construction project can also be found on the project webpage.

Construction zones require extra caution to keep everyone safe – pedestrians, cyclists, drivers, and construction workers. When driving, walking, or biking through the construction area, please be aware of your surroundings, watch for construction crews and other road users, slow down, account for delays, and consider other routes if possible. Learn more about how to stay safe in construction zones.

The speed reduction from 80 km/h to 60 km/h in this area will remain in effect throughout construction for the safety of the public and construction crews.

Thank you for your patience as we complete this necessary work. This work will allow us to continue providing you with high quality tap water and wastewater services. If you have any questions, please contact us.

Wastewater Collection and Conveyance
Engineering Services Division
Public Works, Region of Peel
Email: construction@peelregion.ca
Phone: 905-791-7800 ext. 4409