Peel Region homepage
Peel Region
Go
main

Watermain and sanitary sewer replacement and improvement

Edgebrook Crescent, Edenborough Drive and Exeter Place. Project 20-1340B & 20-2300

The Region of Peel was working in your neighborhood last year to replace the watermain, replace the sanitary sewer, and reline existing sanitary sewer laterals along Edgebrook Crescent, Edenborough Drive, and Exeter Place. This work is required to maintain and improve existing water and wastewater services.

Schedule for remaining construction and repair work

Construction was paused due to freezing temperatures. We expect to start work again on March 1, 2023, to complete the following:

We plan to complete this work by June 2023. This work will be under warranty for two years from the completion date.

Contractor and working hours

The work will be completed by Rymall Construction, under contract to the Region of Peel. This contractor’s normal working hours are from 7 a.m. to 7 p.m., Monday to Friday. These hours are consistent with the local municipality’s bylaws. We understand this may cause some inconvenience, but shorter working days would require your neighborhood to be under construction for a longer period of time.

Sign up for email notices

Receive timely project updates right to your inbox by signing up for e-notices at peelregion.ca/construction

Interrupting your water supply

It is our goal to let you know 48 hours (2 days) in advance if we plan to shut off your water for an extended period (several hours). Occasionally we may have to reduce this notice to 24 hours.

If we need to shut off your water for a short duration (less than one hour), we will knock on your door to notify you.

If we must shut off your water due to an emergency, we will knock on your door to alert you, and do everything we can to fix the problem as quickly as possible.

Areas impacted by construction

Replacing watermains and sanitary sewers usually requires digging a trench within the municipal right-of-way, the land owned by the municipality between the water service box and the street. (The water service box is a small, round, metal valve located outside on the property line between your house and the road.) Depending on the location of the watermain and sanitary sewer, this trench might cause temporary damage to roads, curbs, sidewalks, boulevards, driveway aprons, and lawns within the municipal right-of-way.

To maintain your water supply, the Region of Peel will also replace:

This requires digging up your water service box and will affect an area at least 2m2 around your service box in either your lawn or driveway.

In addition, depending on its condition, the Region of Peel may also repair or replace the municipal portion of the sanitary sewer connection, the smaller underground pipe running from your home to the Regional sanitary sewer system. This may require digging up either the lawn or driveway above this section of pipe and disturbing an area at least 2m2. Any damage caused by Regional construction will be repaired.

We recommend you delay any driveway paving or major landscaping projects until this construction work is completed.

In-ground sprinkler systems

As your front lawn may be affected by this construction work, we strongly recommend moving any sprinkler lines that are located in the municipal right-of-way or next to the sidewalk. If you can’t relocate these sprinkler lines, please send us a map created by your irrigation contractor or flag each sprinkler head that is located within one meter of the sidewalk, curb, or driveway.

Tree trimming

If tree branches within the municipal right-of-way interfere with construction, the trees will be pruned beforehand.

If tree branches on private property interfere with construction, they will be pruned back to the nearest suitable trunk or branch. The contractor will contact you before any pruning of private trees occurs. If you do not allow personnel onto your property to trim the tree, the branches will be cut vertically at the property line.

Repairing areas impacted by construction

We will start repairing the road, curb, sidewalk, driveways, and lawns once the new water service and all sanitary sewer connections to all properties have been completed on your street. Repairs may be delayed due to contractor availability or certain seasonal weather conditions.

For example:

Repairing grassy areas

The contractor will replace any damaged sod (grass) on the boulevard or your front lawn and will take care of the new sod for 30 days. You can help the sod stay healthy by watering it. A longer ‘deep root watering’ works better to establish new sod than watering more frequently for a shorter time. Watering in the early morning allows more water to soak in instead of evaporating.

Repairing driveways

If you would like to have the rest of your driveway paved, please contact the contractor, Rymall Construction, 416-745-0707 x 2227. The contractor will then share contact information for the company hired to do the paving repairs. Please remember this is your option. If you decide to have your entire driveway repaved, this extra paving work is your responsibility and outside the jurisdiction of the Region of Peel.

Driveway access

It may be necessary to block your driveway for a short time when crews are digging the trench for the watermain, replacing your water service box and pipe, digging the trench for the sanitary sewer, working on your sanitary sewer connection, or completing other construction activities. If so, we will knock on your door to notify you. If a trench prevents access to your driveway, the contractor will have metal road plates available to allow access if required. We will make sure businesses always have access. Please contact us if you have special needs related to access.

Waste collection

Your garbage, recycling and organics containers will continue to be picked up on your regularly scheduled day. It is the contractor’s responsibility to move your garbage, recycling, and organics bins from the end of your driveway to a location where waste collection vehicles can pick them up. Empty containers will be returned to their corresponding addresses. Please make sure your house number is clearly marked on each bin.

Vibrations

You could feel slight vibrations from the construction work.

Private-side water service replacement

We are replacing the section of the water service pipe that leads from the watermain to your water service box (small round metal valve near the property line). The privately-owned section of the water service pipe (between the service box and your home/business) is likely the same age and in the same condition. You may want to consider replacing it to ensure a constant supply of high-quality drinking water to your tap. Replacing the private-side water service pipe is the responsibility of the property owner. Peel Region cannot do this work for you. Refer to peelregion.ca/water/your-home/private-side-water-service.asp for more information.

Optional protection plans for your exterior water pipes, wastewater pipes, and in-home plumbing

Many homeowners are not aware that they are responsible for maintaining the water and wastewater pipes both inside their home and outdoors up to the property line. If one of these pipes breaks, it can cause unexpected and costly repairs. The Region of Peel has partnered with Service Line Warranties of Canada (SLWC) to offer homeowners optional, affordable protection from unexpected home repairs. Learn more about the protection plans at plansforpeel.ca

Safety during construction

Construction zones require extra caution to keep everyone safe – pedestrians, cyclists, drivers, and construction workers. When driving, walking, or biking through the construction area, please be aware of your surroundings, watch for construction crews and other road users, slow down, account for delays, and consider other routes if possible. To learn more about how to stay safe in construction zones, visit peelregion.ca/construction/workzonesafety.

Keeping you informed

We will let you know if there are any major changes to the plans.

Information on this project can also be found at peelregion.ca/pw/construction/bram/20-1340B.htm.

Thank you for your patience as we complete this necessary work. This work will allow us to continue providing you with high quality tap water and wastewater services. If you have any questions, please contact us.

Water Linear Engineering and Reliability / Wastewater Collection and Conveyance
Engineering Services Division
Public Works, Region of Peel
Email: construction@peelregion.ca
Phone: 905-791-7800 ext. 4409