Peel Region will be working in your area to replace the watermain along Beech Grove Side Road, as shown on the attached map. Watermains are underground pipes that bring tap water from our water treatment plants to your neighbourhood. As pipes age and our population grows, we need to replace older watermains to keep providing you with high quality water.

Construction schedule

Construction is planned to begin on January 10th, 2024 and be completed by end of April 2024. These timelines are estimates, as weather and other unexpected events may impact our timelines.

All work is under warranty for two years from the completion date.

Sign up for email notices

Receive timely project updates right to your inbox by signing up for e-notices. Visit peelregion.ca/construction/signup.

What to expect during construction

Learn what to expect during watermain construction by visiting peelregion.ca/construction/watermain and watching our short video. The video goes behind the scenes to show what happens before, during and after construction. This website also answers common questions about:

Traffic and parking

We may need to temporarily close roads or reduce traffic to a single lane during construction. If we must reroute traffic, we will place signs giving directions. On-street parking will be reduced during construction when we are actively working on your street.

Interrupting your water supply

We anticipate that this construction project will require temporarily shutting off your water.

For residents:

You could feel slight vibrations from the construction work.

Safety during construction

Construction zones require extra caution to keep everyone safe – pedestrians, cyclists, drivers, and construction workers. When driving, walking, or biking through the construction area, please be aware of your surroundings, watch for construction crews and other road users, slow down, account for delays, and consider other routes if possible. To learn more about how to stay safe in construction zones, visit peelregion.ca/workzonesafety.

Keeping you informed

Information on this construction project can also be found at peelregion.ca/pw/construction/cal/23-1370A1.asp.

We value your feedback

After we have finished, we will invite you to provide feedback on the construction project.

You can sign up to receive this survey electronically at peelregion.ca/construction/signup

Thank you for your patience as we complete this necessary work. This work will allow us to continue providing you with high quality tap water. If you have any questions, please contact us.

Water Linear Engineering
Engineering Services Division
Public Works, Region of Peel
Email: construction@peelregion.ca