Sanitary pumping station replacement
Silver Birch Trail and Marshwood Place Project 16-2905, Assignment 1
Project updates
What are we doing?
- Replacing and improving the aging sanitary sewer pumping station located at the end of Silver Birch Trail.
Why?
- To upgrade the wastewater system capacity and reliability as part of the Region of Peel’s State of Good Repair program. Pre-existing-conditions-survey-letter.
When?
- We expect to start work on March 23, 2023.
- The project should be completed by end of 2024. All work is under warranty for two years from the completion date.
Contact information
- Email: construction@peelregion.ca
- Phone: 905-791-7800 ext. 4409
Working hours
- Our contractor’s normal working hours are from 7 a.m. to 7 p.m. These hours are consistent with the local municipality’s bylaws. We understand this may cause some inconvenience, but a shorter working day would mean the project would take longer to complete.
Traffic, driveway and parking control
- All roads within the project limits will always remain open to traffic however we may need to temporarily reduce traffic to a single lane during some portions of the work.
- Due to construction activities, we may need to block your driveway for a short time. We will contact you before we do this to arrange for the best time and for alternate access, if needed.
- On-street parking will be reduced during construction.
Irrigation or sprinkler systems
- Please tell the inspector if you have underground irrigation or a sprinkler system outside your property line.
Trees
- If tree branches within the right-of-way interfere with construction, the contractor will have the trees pruned before equipment enters the drip line of the tree.
Vibrations
- You may feel slight vibrations from the construction work.
Replacing and taking care of your sod
- The contractor will replace disturbed sod after completion of construction activities on the site.
- You can help the sod to stay healthy by watering it for one hour in the early morning, two or three times a week. This is especially important in hot or dry weather.
- We will replace your sod as soon as we can, but there may be a short delay.
Project updates
- The Region of Peel will always let you know if there are any major changes to the plans.