Winter shutdown update
Crystalburn Avenue., Fendalton Street. and Appledore Crescent. Project 20-1310 H
What we are doing
- Due to the cold weather and forecast we were unable to complete the project as anticipated.
- To date we have completed the watermain replacement in your area and have yet to complete the installation of a few services and final restoration.
- We have left the construction site in a safe condition for the rest of the winter.
When will we be back
- We expect to start work in the first week of January 2022.
- Works should be complete by June 2022.
Who you can call
Region of Peel Personnel | ||
Contact | Responsibilities | Telephone |
---|---|---|
Mark Masley | Project Manager | 289-541-6689 |
George Da Re | Inspector | 905-791-7800, ext. 3246 |
Timbel Construction Timbel Construction will do the work, under contract to the Region of Peel |
||
Contact | Responsibilities | Telephone |
Vince Bellisimo | Project Manager | 416-747-1788 |
Bruno Bellissimo | Site Superintendent | 416-747-1788 |
Project updates
- The Region of Peel will always let you know if there are any major changes to our plans.
- We will try to disturb you as little as possible.
- Please call the Project Manager or Inspector if you have any problems or special needs.